Minds → Crane & Rigging → How often must rigging equipment be inspected under 29 CFR 1926.251, and what happens to defective equipment? Answer in under 100 words.
US FederalOSHA Construction Standard

How often must rigging equipment be inspected under 29 CFR 1926.251, and what happens to defective equipment? Answer in under 100 words.

Under 29 CFR 1926.251, rigging equipment must be visually inspected prior to use on each shift and as necessary during use. Any defective rigging equipment must be immediately removed from service and cannot be used again until it is repaired or replaced.
Last verified: 2026-08-26 · Sources checked: 1/1 resolving · Next scheduled review: 2026-11-24

Details / How it works

29 CFR § 1926.251(a)(1) requires that all rigging equipment (including slings, hooks, shackles, grabs, clamps, and similar accessories) intended for material handling be visually inspected prior to use on each work shift and as necessary during use to ensure safe condition. The employer is responsible for ensuring these inspections are performed.

When equipment is defective:

  • The standard explicitly states: "Defective rigging equipment shall be removed from service" (§ 1926.251(a)(1)).
  • It remains out of service until repaired or replaced (§ 1926.251(a)(1)).

Numbers & thresholds

Requirement Detail
Inspection frequency – general rigging Prior to use on each shift and as necessary during use
Inspection frequency – slings (daily) Each day before use by a competent person; additional inspections during use as warranted
Defective equipment action Immediately removed from service; not reused until repaired or replaced
Alloy steel chain sling periodic inspection At least once every 12 months, with records maintained (§ 1926.251(b)(6))

Exceptions & edge cases

Slings have additional inspection requirements:

  • Daily inspection: Each day before use, a competent person designated by the employer must inspect the sling and all fastenings and attachments for damage or defects (§ 1926.251(a)(6)).
  • Alloy steel chain slings require a thorough periodic inspection at least once every 12 months, with the employer maintaining a record of the most recent month of inspection (§ 1926.251(b)(6)).
  • More frequent inspections are required if service conditions (e.g., high loads, abrasive materials) warrant.

Sources

  1. [1]U.S. National Archives, Electronic Code of Federal Regulations — 29 CFR 1926.251 — Rigging equipment for material handling · as of 2026-08-26

Ask this MIND

This answer is static and source-locked. Ask Crane & Rigging your version of this question.

Related questions

This is general information, not advice. Crane & Rigging summarizes primary sources (OSHA, NIOSH) as of the dates shown. It is not tax/legal/immigration advice and doesn’t account for your situation. Consult a qualified professional before acting. About this MIND

This page is one mind’s knowledge, published.

MIND turns your documents into a queryable, citable knowledge graph.

Make your own MIND →
Content licensed CC BY 4.0 · Attribution: "Source: MIND (m-i-n-d.ai)" · License terms
© 2026 MIND · m-i-n-d.ai · All Minds · Crane & Rigging · License · Privacy · Terms